    Please help me regading adding up time in an actual date in P6.  For example, actual start date is 09-Sep-10 00:00A. I am supposed to add up time at the end of each actual date. For examaple, 09-Sep-10 08:00A for actual start date and 11-Dec-10 16:00A for the finish date.  I'm doing it manually and I am already tired and messing up a lot. I hope anyone out there can help me regarding my problem.

    Thanks in advance.


    Regards,
    Darwin
    Zoltan PalffyUser is Offline
    Master Member
    Master Member
    Posts:2427
    Avatar

    --
    12 Apr 2011 03:11
    for automatic updating go to
    1. Choose Tools, Apply Actuals.

      The Project(s) To Be Updated section lists all the projects you can update, along with the current data date and the planned start for each project.
       

    2. Specify whether to use the same data date for all projects or whether each project uses its own data date.

    3. In the New Data Date field, click Browse button and select the new data date or click Previous button or Next button to select a new data date based on timesheet end dates.

    4. Specify whether to recalculate the remaining duration based on the activity duration type or to always recalculate. If you choose to always recalculate, all activities are treated as Fixed Units and Fixed Units/Time.

    5. Click Apply.


    Zoltan Palffy
    Dr. House of Scheduling
    Jeason GeorgeUser is Offline
    New Member
    New Member
    Posts:3
    Avatar

    --
    23 Aug 2011 05:33

    Hi Darwin

    How r u? Hope u remember me. This is Jeason from Qatar.  Nice to see u here