Progress Update Problem
Last Post 06 Feb 2012 03:20 by Zoltan Palffy. 54 Replies.
Printer Friendly
  •  
  •  
  •  
  •  
  •  
Sort:
PrevPrev NextNext
You are not authorized to post a reply.
Page 3 of 3 << < 123
Author Messages
Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
02 Nov 2011 01:31
Dear Sir,

good day sir...i am stuck in a problem of updating progress and i need to submit monthly report ..
every thing is alright except some bars which are showing bar neck (giving the impression that it is nonworking time) but other bars at the same period showing full bar
sir plzzz guide me how to solve this probelm...?
waiting for your kind responce


Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
02 Nov 2011 11:48
could be a couple of thiings

1. check all of your bars go to view ars then choose a bar and look at the Bar Settting tab and make sure that there are no boxes check under the Bar necking setting

also look at your calendars they may be different


Zoltan Palffy
Dr. House of Scheduling
Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
07 Nov 2011 00:47
SIR!!
i have already checked my calander it is same for all activities
in the setting i myself check the bar neck setting but if there is any nonwork that should be same for all bar.. but
the below is the detail of the problem
in status tab when i update actual data under duration head e.g.
actual duration = 72
i put remaing duration = 308
at completion it should be 380 but is showing 420.....thats y bar neck is there i could not fix this problem
please help sir...?



Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
07 Nov 2011 02:43
need to see all of this in detail to correct your problem

please take screen shots of calendars

and bar necking settings

and the duration that you speak of





Zoltan Palffy
Dr. House of Scheduling
Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
14 Nov 2011 22:12
Dear Sir,

as per your advise i have attached bar neck setting, duration problem and calander.

please help resolve this problem!!!

Regards

Muhammad Saqib

calander.png
duration_problem_examples.jpg
bar_neck_setting.png

Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
14 Nov 2011 22:24

attachments here

reagrds

Muhammad Saqib


bar_neck_setting.png
calander.png
duration_problem_examples.jpg

Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
15 Nov 2011 03:26
sorry the screen shots are too small I can not read them


Zoltan Palffy
Dr. House of Scheduling
Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
15 Nov 2011 21:00
Dear Sir,

hope this attachemnt will work

waiting for your kindness

Regards

Muhammad Saqib

Duration_Prob.pdf
bar_neck_setting.pdf
calander.pdf

Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
16 Nov 2011 02:56
almost I need to you to highlight the two bars the actual work bar and the remaining work bar

and see the bar settings

the screen shots that you attached were the bare setting for remaning level of effort

as far as the durations are concerned I they look ok but you need to look at the predecessors to the work and see if it is holding up the reaming portion of uncompleted work


Zoltan Palffy
Dr. House of Scheduling
Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
16 Nov 2011 03:49
Dear Sir,

i am sorry for the wrong selection for level of effort activity now i have attached the correct information.
also i have put one predessor example for your information may b i will help more to understand

although your idea regarding the predessor may be most probable situation in this case.

thanks sir!!!!

predessor_example.pdf
bar_setting.pdf

Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
16 Nov 2011 04:00
I would need to se the file send the xer to

zoltan.palffy@
mcdean.com


Zoltan Palffy
Dr. House of Scheduling
Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
16 Nov 2011 04:20
Thanks in advance sir,

i have send the email please check...

regards

saqib


Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
04 Feb 2012 20:50

Good day Sir... Zoltan

i have a querry regarding the duration % complete

if i put duration percent complete e.g 50% the percent complete bar increase by 50% but y the remaining work bar decrease by same percentage


Duration_%_Complete_Problem.png

Saqib ParachaUser is Offline
Senior Member
Senior Member
Posts:200
Avatar

--
04 Feb 2012 21:19
may b this attachment will work

Regards

saqib

Duration_%_Complete_Problem.pdf

Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
06 Feb 2012 03:20
that is correct is you have a 10 day activity and it is 50% complete

then you only have 5 days remaining


Zoltan Palffy
Dr. House of Scheduling