Lag Logic Calendar Accounting Days
Last Post 19 Sep 2011 07:24 by Zoltan Palffy. 1 Replies.
Printer Friendly
  •  
  •  
  •  
  •  
  •  
Sort:
PrevPrev NextNext
You are not authorized to post a reply.
Author Messages
Chris CrainUser is Offline
New Member
New Member
Posts:5
Avatar

--
15 Sep 2011 10:35
    I have the following situation with lag logic calendar accounting days:

    Activity 1   SS-10D to Activity 1A
    Activity 1A Start on Oct 10. 
    Activity 1   shows Starting on Oct 3 with a 5D work week calendar. Even if I count weekends this is still only 7days.

    Activity 1   - 5D Work Week Calendar
    Activity 1A - 7D Work Week Calendar

    Why isnt Activity 1 indicating Sept 26?

    Thanks
    Zoltan PalffyUser is Offline
    Master Member
    Master Member
    Posts:2427
    Avatar

    --
    19 Sep 2011 07:24
    the most important things that you forgot to mention here is what is your data date ?

    and are you using NEGATIVE LAGS if so there is your problem you NEVER EVER USE NEVATIVE LAGS

    even is you use nevative lags it does not matter what the actual date is on activity 1A that is history.

    I bet that activity 1 start date is the same as your data date
    Zoltan Palffy
    Dr. House of Scheduling