Importing from P6 to PertMaster
Last Post 04 Mar 2012 20:10 by M Syahrul Azman. 2 Replies.
Printer Friendly
  •  
  •  
  •  
  •  
  •  
Sort:
You are not authorized to post a reply.
Author Messages Not Resolved
Mobeen AkhtarUser is Offline
New Member
New Member
Posts:1
Avatar

--
09 Jan 2012 01:19
    When importing P6 xer (plan) to Pertmaster (primavera risk analysis) for risk analysis the import dialogue box appeared. Through that I fixed the problem of increase in project finishing date by selecting planning unit as hour, by avoiding rounding off. But i have still the below problem in imported schedule in pertmaster:

    1. Remaining duration it's showing is higher then plan, 1541 against 505 ( but less then project duration x 8 hr/day)
    2. Original duration is zero, 0 against 1078
    3. In my P6 schedule settings, total float = finish float, and showing zero total float for project. Whereas in Pertmaster it's showing -ive float, -667 against zero.

    MyP6 plan has no -ive float and without constraints. Also in pertmaster project end date is same as P6.

    Any advise

    Thanks
    Mobeen
    svbUser is Offline
    Basic Member
    Basic Member
    Posts:27
    Avatar

    --
    17 Jan 2012 04:52
    WHEN YOU ARE IMPORTING TO PRA, SELECT PLANNING UNIT AS HOUR INSTEAD OF DAY. IF PROBLEM DOES NOT SOLVE, PLEASE UPLOAD YOUR P6 FILE FOR FURTHER INVESTIGATION.
    M Syahrul AzmanUser is Offline
    Basic Member
    Basic Member
    Posts:12
    Avatar

    --
    04 Mar 2012 20:10
    Hi,

    do you know how to stop PRA from automatically change/rounding the durations & lags?
    You are not authorized to post a reply.