Engineering Schedule Templates
Last Post 16 Apr 2012 19:43 by quoc anh hoang. 81 Replies.
Printer Friendly
  •  
  •  
  •  
  •  
  •  
Sort:
PrevPrev NextNext
You are not authorized to post a reply.
Page 4 of 5 << < 12345 > >>
Author Messages
Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
20 Feb 2012 13:08
I don't think the Graph is understandable for boss, report will be better to present him.

To show how many labour are actual (in numbers) and how many we neeed in tabular chart would be better what do you suggest

for the above i would appreciate if you tell me the report's ID in reports section.


Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
20 Feb 2012 13:30
disagree a graph is always easlier to read and understand that just plan numbers.

Graphical is always better.


Zoltan Palffy
Dr. House of Scheduling
Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
21 Feb 2012 07:11
Kindly Tell me how to add/use RESOURCE section under an activity details.

for example:
Cable pulling is one activity ..... required 6 days duration and 1340 Meter wire. then how to add in resource column.


i have added like this: Labour 6, Cable (Equipment and Measures as METER)

is it okay?


Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
21 Feb 2012 07:11
Kindly Tell me how to add/use RESOURCE section under an activity details.

for example:
Cable pulling is one activity ..... required 6 days duration and 1340 Meter wire. then how to add in resource column.


i have added like this: Labour 6, Cable (Equipment and Measures as METER)

is it okay?


Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
21 Feb 2012 11:15
I have given you 3 different ways to add resources

see detailed instruction below

resourceshowto.pdf
001_part1resourcesandcosts.pdf
002_001_part2resourcesandcosts.pdf

Zoltan Palffy
Dr. House of Scheduling
Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
22 Feb 2012 08:01
Thank you very much for the detailed answers, now i have two questions more:

1. In my resource usage profile preview i don't see them in a hirarichal format (Indent / Outdent) so how can i make/convert in a hirarichal format because i have to check overall chart and in usage spread sheet i want to see the total number of manpowers. Current due to unavailability of indent/outdent i am unable to see that.

2. Can i only see the specific WBS (even that is sub-wbs) i have no concern with activities in progress/done etc.. i just want to see only two sub-wbs with their all acitivities ........under many WBS. How can i do that?


Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
22 Feb 2012 08:01
Thank you very much for the detailed answers, now i have two questions more:

1. In my resource usage profile preview i don't see them in a hirarichal format (Indent / Outdent) so how can i make/convert in a hirarichal format because i have to check overall chart and in usage spread sheet i want to see the total number of manpowers. Current due to unavailability of indent/outdent i am unable to see that.

2. Can i only see the specific WBS (even that is sub-wbs) i have no concern with activities in progress/done etc.. i just want to see only two sub-wbs with their all acitivities ........under many WBS. How can i do that?


Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
22 Feb 2012 10:42
1. You cant see them in a hirarichal format unless you have set them up that way in the resource mode

2. Group my wbs the select select view then select collapse to then select the level that you want to collapse to.
 


Zoltan Palffy
Dr. House of Scheduling
Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
22 Feb 2012 11:06
I went in sort and tried by WBS but it's not giving me the desired result.

Let me explain you again.

My first WBS is ABC then under this WBS there are Five WBS and each have different activities.

I want to only see the PIPING WBS that is located in (Five WBS). My boss only want to see PIPING WBS in the schedule not any other how is it possible?


In RESOURCE spreadsheet, how can i copy the numeric values into the excel file to make some changes?


Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
22 Feb 2012 11:28
Activity Usage Spreadsheet: You can only copy the statistics value from this section.

Is there any other way to copy these numeric values?


Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
22 Feb 2012 14:11
these arre two different questions

filter for the wbs you want 

highlight the resource for the piping work

you can export the values to excel what values do you want to import ?


Zoltan Palffy
Dr. House of Scheduling
Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
22 Feb 2012 14:12
see attachment



001_p6settingexportimportbudget.pdf

Zoltan Palffy
Dr. House of Scheduling
Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
23 Feb 2012 01:45
I have gone through with the attachment but i knew this a little bit because i checked your site in details so i found good data too as this whole website has a very good material.

But I am still confused to sort out by WBS showing activities (total under sub-wbs) i am unable to do so.

second question is that i created a pool in a hirarichal way but when i click on resource usage sheet or graph i don't find my resources in that format, it displays all in a series way like all are OUTDENT. so how can i do that and tell me also how can create a resource pool in a project. i mean is there any option? e.g. we have different options in other area from global to project so does it have any?


Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
23 Feb 2012 03:08
1st answer: filter where wbs is whatever you want hopefully your wbs structure is setup correctly

2nd answer: if you are looking at the resources profile make sure that on the left had side that you select the upside triangle and the filter by current project resources is selected. However you will only be able to see the the current project resoures if you have actually assigned them to an activity.

What I mean is that if you creat a resouces and no not actually assign to at least one activity then it will not show up when you select the upside triangle and then select filter by current projects resources.

see attachement

parentchildresources.pdf

Zoltan Palffy
Dr. House of Scheduling
Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
29 Feb 2012 20:26
How to take a PRINT the specific WBS?

e.g.: there are so many milestones and under them there are so .... and i want to get some prints (hard copies) for some of them to check so is there any way to print out those specific WBS??

Kindly let me know.


Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
29 Feb 2012 20:28
sorry REPLACE the word milestones with WBS and under WBS there are many sub-wbs and activities and i want to check them in a hard copies.


Zoltan PalffyUser is Offline
Master Member
Master Member
Posts:2427
Avatar

--
01 Mar 2012 03:34
filter for the wbs that you want and print it


Zoltan Palffy
Dr. House of Scheduling
Syed ZaidiUser is Offline
Basic Member
Basic Member
Posts:44
Avatar

--
05 Mar 2012 04:13
No, i am unable to do so anyway i know there is no way because after using that filter that WBS will be visible. i wanted to hide that WBS and their activities same as we can do in Excel (If applying filter).

Now I have another question:

Is there any way to define a contraint on WBS or sub-wbs? because i am using constraint but when i schedule the dates are changing and i don't want to change because engineers have given me their dates so how can i stop this? please help.


Toan Tran ThanhUser is Offline
New Member
New Member
Posts:3
Avatar

--
09 Apr 2012 00:12
Hi everybody Im Newer in primavera. I working with resource, in budgeted costs I enter the value brought to 0 fails all I have to be entered several times. What happen ?. Sorry I speak english not good.


Toan Tran ThanhUser is Offline
New Member
New Member
Posts:3
Avatar

--
09 Apr 2012 00:13
Posted By Toan Tran Thanh on 09 Apr 2012 01:12
Hi everybody Im Newer in primavera. I working with resource, in budgeted costs I enter the value brought to 0 fails all I have to be entered several times. What happen ?. Sorry I speak english not good.